Highway Projects FY 2013

Scheduled for Construction

For detailed information on specific local projects, click on "green" PID number in the far right column. 

Location

Project

Sponsor

Description

PID

Fisher Road ACEO Replace structure over the Ottawa River 200 feet south of rear approach to 500 feet north of forward approach.  82050
Bellefontaine NE Market Corridor Lima Replace existing pedestal mount signals with decorative mast arm mounts.  Replacement of existing galvanized steel light poles/cobra heads with decorative street lighting and landscaping.  89397
SR 117/309 ODOT Improve safety of corridor by designing and constructing recommendations made from corridor study.  Safety improvements include, but are not limited to: signal coordination, raised concrete curb median east of IR75 along SR309, driveway definition through SR117 from .02 miles west of Rouschman Road jucntion to Greely Chapel Road junction.  SR 309 from Williard Avenue to Devonshire Drive.   75467
US 30 ODOT Resurface US30 by grinding 1.5" and paving 1.5".  Some joint repair may be required.  Begin at forward end of the rialroad bridge at log 13.31 and end at the concrete pavement east of the Napoleon Road bridge.  75518
IR 75 ODOT Major rehabilitation on IR75.  Reconstruction from mile marker 5.53 through SR81 interchange.  Geometrics to be corrected and capacity needs analyzed.  76691
SR81 ODOT Two lane resurfacing from SR81 and IR75 junction to the Hardin County line.  80492
IR 75 ODOT Major rehabilitation on IR75.  Reconstruction from Auglaize County line through mile marker 5.53.  Geometrics to be corrected and capcity needs analyzed.  89029
ALL/PUT SR 65 ODOT Resurface with asphalt concrete SR 65 from junction SR 115 to the north corporation limit of Columbus Grove  91916